Asbestos remediation contractor drafts control plans and SWMS with AI

We built an asbestos removal control plan system with AI for a WA remediation contractor: job facts come from ServiceM8, AI drafts the plan, code fills the required sections and calculations, and a qualified person reviews each one. Crews then read and sign off the plan and SWMS on a phone, written back to the ServiceM8 job. The team drafted 261 plans from May to October 2026, at a median of 44 seconds each.

Published

Outcome

  • 261 Asbestos Removal Control Plans drafted in production, May to October 2026 Production database count, October 2026.
  • 90% Of plans started in the app produced a finished Word document Production funnel review, August 2026.
  • 44 s Median time to draft a full control plan Model monitoring logs since May 2026 (202 generations).

How it works

  1. 01Pick the job

    Site, scope, dates and supervisor come across. (ServiceM8 and Word)

  2. 02Describe the work

    The user explains the job in plain English. (Qualified reviewer)

  3. 03Draft the narrative

    Gemini writes the job-specific plan text. (Google Gemini)

  4. 04Fill and check

    Sections, sizing and working days from the rules. (Rules engine)

  5. 05Review and sign off

    A qualified person edits, then exports Word and PDF. (Qualified reviewer)

    Sign-off
  6. 06Crew reads and signs on site

    Each person acknowledges the version on a phone. (Field crew)

    Sign-off
  7. 07Written back to the job

    ServiceM8 holds who signed what; the office sees it live. (ServiceM8 and Word)

At a glance

Client
Asbestos remediation contractor
Industry
Asbestos remediation
Workflow
ARCP and SWMS documentation
Built with
Google Gemini drafting, rules engine, Word export and phone sign-off
Systems
  • ServiceM8
  • Google Gemini
  • Supabase
  • Trigger.dev
  • Vercel
  • Microsoft Word
Delivered
May 2026

The challenge

Every asbestos removal job in WA needs an Asbestos Removal Control Plan (ARCP) and a Safe Work Method Statement (SWMS) that fit the site, the material and the removal method. The team copied an old plan and hoped the job was similar, or wrote one from scratch, retyping site, scope and dates already held in ServiceM8.

For anything beyond a simple job the client put it at 30 to 60 minutes per document set, and only experienced people knew how to structure a plan that WorkSafe WA and the building owner would accept.

One template across every job meant plans that read as generic. A friable removal inside an enclosure, work at height and a site next to occupied rooms each need different controls, and the document had to show that. Senior staff were writing this paperwork instead of supervising sites.

On site, crews worked from printed copies that could be lost, soaked or out of date if the plan changed after they left the depot. Handwritten pre-starts and sign-offs took 20 to 30 minutes per crew a day, and processing that paper took the office another 2 to 3 hours a day, both by the client's own estimate. Nothing proved a removalist had read the plan for the job they were on.

Before and after
AspectBeforeAfter
Starting pointCopy an old plan or start from scratchJob facts pulled from ServiceM8
Sections and sumsWorked out by hand, remembered by senior staffComputed, filled and checked by code from the rules
Time per set30 to 60 minutes (client's own estimate)Draft in 44 seconds; review time about 10 min
Crew sign-offHandwritten, 20 to 30 min per crew per dayTap to confirm on a phone, about 5 min per crew per day

What we built

We read 126 of the client's past control plans and 121 SWMS and wrote their structure down as rules. Google Gemini writes only the job-specific narrative; code produces everything that must be exact; a qualified person reviews and approves every plan.

The user picks a job from ServiceM8, describes the work in plain English in a chat, and the system drafts the plan as a background job. Sections, enclosure sizing, working days and standard wording come from the rules, and the plan opens in an editor where each change is logged. Plans export to Word and PDF from the client's own template. The system does not certify a plan or send anything to the regulator, which keeps responsibility with the person who signs it.

On site, each crew member opens the plan and SWMS for their assigned ServiceM8 job in the phone browser, with no app to install. They confirm arrival, acknowledge each document against the version they read, and the crew signs off. Confirmations are written back to the ServiceM8 job, and an office dashboard shows arrivals and sign-offs within seconds. There is no AI in this step; the sign-off is a person's, recorded by rules.

Systems and what each one does
ServiceM8Source of the job facts (site, scope, dates, supervisor) that start each plan, and the record that receives each crew's arrival, acknowledgement and sign-off.
Google GeminiDrafts the job-specific narrative from the job facts and the user's description.
Rules engineRequired sections, standard wording and calculations, specified from 126 real plans.
SupabaseHolds plans, edit history, user accounts, and each crew acknowledgement with who, when and which document version.
Trigger.devRuns each drafting job in the background, so the user is not left waiting on a page.
VercelHosts the web app the safety team signs in to, its phone views for crews and the live office dashboard.
Microsoft WordPlans are produced as Word and PDF from the client's own template.

Results

Live since May 2026 and used more each month. 90% of plans started in the app became a finished Word document, and three in four were edited by the reviewer first.

At the field end, a crew member's confirmation now names the person, the job, the time and the version of the plan and SWMS they read. The office stops phoning the field for status, and ServiceM8 carries the same record against the job, ready for an audit without anyone re-keying paperwork. On the client's own before figures, the sign-off is projected to save about 32 office hours a month.

Return on investment

Projected
Saving
35 hrs a month
Payback
6 months

Before: 30 to 60 minutes to prepare one control plan and SWMS set, the client's own description in the signed proposal (not timed). After: about 10 minutes of review per set, at about 60 sets a month and $90 an hour, against a midpoint of 45 minutes before (projected).

Control plans drafted per month, 2026
May: 11 plans Jun: 38 plans Jul: 51 plans Aug: 57 plans Sep: 103 plans

Production database count by month the plan was started (May from 12 May).

Show data
Itemplans
May11
Jun38
Jul51
Aug57
Sep103
Results
261 Asbestos Removal Control Plans drafted in production between May and early October 2026.Production database count, October 2026.
90% Of 138 plans started between May and August produced a finished Word document; 74% were edited first.Production funnel review, August 2026.
44 s Median time to draft a full control plan, at about US$0.06 in model cost per generation.Model monitoring logs since May 2026 (202 generations).
20–30 min Field sign-off: crew time per day on handwritten pre-starts and sign-offs before.Client's own estimate, signed proposal.
2–3 hrs Field sign-off: office time per day processing paperwork captured on site before.Client's own estimate, signed proposal.
600 Field sign-off: crew sign-offs recorded on phones.Projected from the build.
5 min Field sign-off: crew time per day on sign-off now.Projected from the build.

What we’d do again

  • Let code own anything that must be exact. Calculations, required sections and standard wording come from rules built on 126 real plans; the model only writes the parts that change job to job.
  • Measure before switching. A faster single-step generation passed every format check but dropped enclosure stages on friable-asbestos test jobs, so it shipped only after being re-scoped.
  • Fill the gaps users hate. SWMS drafts went out with too many blank fields and use stalled until those fields were filled from the job data.
  • Keep the sign-off human. The system does not certify a plan or submit one to WorkSafe WA; a qualified person reviews each document and answers for it.
  • Tie every crew acknowledgement to a document version. Plans can change after a crew leaves the depot, so the record shows which version each person actually read.
  • Reuse the web app, skip the native one. Crews sign in on a phone with the accounts they already have, so there was no second system to keep in step with the office one.
  • Plan for patchy signal without promising offline mode. Short gaps queue and sync when coverage returns; extended offline document caching, photo capture and GPS check-in were left out of the first scope.